Installing a Floating Engineered Hardwood Floor

Because of its construction, engineered hardwood brings with it a number of advantages including quick installation.

This project focuses on installing a floating engineered floor. Float, Glue and Nail installation are three main methods used for installing this type of floor. Float Installation: The plank pieces are glued (or clicked together if the flooring has a click lock system) to each other but not to the subfloor, creating a single large panel held in place by friction and its own weight. Works well on a wide variety of subfloors.

SEE ALL THE STEPS

  •  There are 9 steps to completing this project:
    Step 1  PREPARE THE FLOOR FOR INSTALLATION
    Step 2  SNAP A CHALKLINE AND NAIL GUIDEBOARD
    Step 3  LAY THE STARTER ROW
    Step 4  COMPLETE THE FIRST ROW
    Step 5  INSTALL THE FIRST PLANK ON THE SECOND ROW
    Step 6  INSTALL THE REMAINING FLOOR
    Step 7  COMPLETE THE LAST ROW
    Step 8  REMOVE THE GUIDEBOARD
    Step 9  INSTALL BASEBOARD
MATERIALS YOU WILL NEED

  • 6mm Plastic Sheeting
    Foam Underlayment
    Adhesive
    Engineered Hardwood Flooring
    Transition Strips
    Flooring Filler
TOOLS YOU WILL NEED

  • Broom
    Hammer
    Nail Set
    Table Saw
    Jigsaw
    Face-Nailer
    Side-Nailer
    Pry Bar
    Tape Measure
    Chalkline & Chalk
    Jamb Saw
    Drill with 1/16" Bit
    Countersink Bit
    Floor Mallet
    Nail Gun
    Tapping Block

Because of its construction, engineered hardwood brings with it a number of advantages including quick installation. This project focuses on installing a floating engineered floor.Float, Glue and Nail installation are three main methods used for installing this type of floor.

Float Installation: The plank pieces are glued (or clicked together if the flooring has a click lock system) to each other but not to the subfloor, creating a single large panel held in place by friction and its own weight. Works well on a wide variety of subfloors.

Project Details

Skill Level: Intermediate

Time: 4 hours

9 Steps

1. Prepare the Floor for Installation
2. Snap a Chalkline and Nail Guideboard
3. Lay the Starter Row
4. Complete the First Row
5. Install the First Plank on the Second Row
6. Install the Remaining Floor
7. Complete the Last Row
8. Remove the Guideboard
9. Install Baseboard

Before You Start, Read This

 


1  PREPARE THE FLOOR FOR INSTALLATION


If installing the floor over concrete, lay 1/4" (6mm) plastic sheeting over the concrete and overlap the seams by at least 8" (20cm). If the concrete is below grade, bring the plastic at least 4" (10cm) up the wall. You will trim it off at the height of the baseboard once the flooring has been installed. Roll out the manufacturer's recommended foam underlayment, but do not overlap the seams.


2  SNAP A CHALKLINE AND NAIL GUIDEBOARD


Add the width of the first two rows to the size of the expansion gap (The distance between the edge of the last plank in a row to the wall). Check manufacturer guidelines for gap distance. Snap a chalkline this distance from the wall and nail a straight board, temporarily along it, to align the flooring.


3  LAY THE STARTER ROW


Apply a bead of glue to the tongue on the end of the first plank following the manufacturer's specifications. Put the grooved edge against the guideboard. Put the grooved end of the next plank against the glued tongue. Seat it by tapping with a hammer and a tapping block that's recommended by the manufacturer. Leave the recommended expansion gap. Apply glue to the end tongues with each additional board to complete the row.


Complete the First Row

4  COMPLETE THE FIRST ROW


Cut the last board of the first row to fit, leaving the recommended expansion gap. Push the board into place with a pry bar, protecting the wall with a putty knife or a scrap piece of wood. A pull bar can also be used for this task.


5  INSTALL THE FIRST PLANK ON THE SECOND ROW


Begin the second row with the piece cutoff from the first row. This keeps the ends of the planks from lining up, creating both a stronger and better-looking floor. Trim the piece of cutoff, if necessary, so the end will be 24" (61cm) from the end of the neighbouring plank. Run a 1/8" (3mm) bead of glue along the tongue of the previous row, put the cutoff against it, and seat with a tapping block.


Install the Remaining Floor

6  INSTALL THE REMAINING FLOOR


Apply glue to the tongues and nestle each board against its neighbour. Seat the edge with a tapping block then seat the end. Cut the last piece of the row to fit, leaving the proper expansion gap between the plank and the wall. Push the last board of each row into place using the same method from Step 5.


Complete the Last Row

7  COMPLETE THE LAST ROW


Measure and cut planks to the width of the distance from the second last row to the wall, allowing for the expansion gap. Rip the boards to measured width to be cut and temporarily put them in place. If the irregularities in the wall result in an expansion gap that is too small, scribe the boards.

To scribe: i. Hold the edge piece parallel to the layout line, setting where it touches the wall at least at one point. ii. Set a compass to the amount you want to remove. iii. Cut along the line with the saw appropriate for engineered flooring. Bevel the cut so the blade trims more off the bottom than the top.


Remove the Guideboard

8  REMOVE THE GUIDEBOARD


Remove the guideboard and install the rows needed to fill in the resulting space. When you reach the row against the wall, rip it to width, as in Step 7, and scribe, if necessary (See Step 7). Install the boards and avoid walking on the floor for at least 8 hours until the glue dries.


Install Baseboard

9  INSTALL BASEBOARD


Install baseboard around the room to cover the expansion gap and protect the walls. See DIY Projects Installing Baseboard;Part 1, Part 2, Part 3 and Part 4.